NHS - Windows Deployment
With aging operating systems and devices, the Buckinghamshire Healthcare NHS Trust were looking to support care provision with an technology investment.
High Level Scope
The provision of a fixed price scheduling, deployment and project management service to undertake the migration of end user clients to the Microsoft Windows10 platform - this included
- Project Management
- Provision of stakeholder engagement and project communications across the initiative
- Co-ordination and scheduling of the identified end users across the Trust
- Build, deployment and early support & training of the new Windows10 environment
- More than 8,000 end users and devices migrated
- 75% completed in 6 months; completion within 9 month deadline from initiation
- Complex mix of Trust locations: Large regional hospitals; healthcare centres, user home deployments
Key Challenges
- Rapid mobilisation and tight timescale for completion
- Complex variety of site locations
- Applications assurance and remediation across the Trust prior to deployment – across a wide number of critical applications
- Minimise disruption to the end users and to the provision of Healthcare across the Trust
- Completed within the context and challenges of the Covid-19 pandemic
Highlights
- Delivered the project safely
- No operational disruption
- Met timescale deadlines
- Delivered within the fixed cost commitment
- Enabled the end user community with WIndows10 and with new functionality
- Improved the integrity and reliability of the end user platform
Key Metrics
- 8,000 end users deployed
- Over 6 Trust locations
- 9 month timeline
Get in Touch